Major structural work complete!

With the major structural work complete, all the windows are now in, half the bedrooms have been plastered and 40% of the steel work for balconies is completed.

It's still a very busy site of course with roofers still hard at work, electricians have 75% of the first fix complete and plumbers are halfway into the fitting and testing of the first fix.

You can see a lot of this progress in these pictures, especially the glazed link passage on the first floor at the rooftop garden which is going to be an amazing and unique feature for our residents, staff and visitors to enjoy.